Construction on the Coming Home projects has nearly finished! Here are the latest changes at Springbrook:
• The 3 new residences for the Golisano School Program are complete. They were turned over to Springbrook on Sept 1, 2011
• The Golisano School addition to the School at Springbrook was completed and turned over on Oct 29, 2011
• Renovations to the gymnasium and cafeteria are about 50% complete with a scheduled turnover of March 2012
• The infrastructure portion of the project was completed in July 2011
• Site contractor, ZMK, has pulled off the job until spring, having completed all but two scheduled projects