The week of October 12-17, 2010 will be very busy as
ZMK Construction works on multiple areas of the
Springbrook Main Campus.
Construction Timeline
Remediation will start on the school beginning 10/11/10 and will continue for up to 10 days. The areas of the school under construction are
highlighted in purple on this map.
NOTE: There will be considerable noise involved with the removal of the waterproofing materials and excavation along the existing foundation.
The stairs leading from the School's west side up to Sunshine and Snell houses will be removed sometime between Tuesday, October 12 and Friday, October 22 as a part of the remediation. Because of heavy construction traffic on the upper road, staff and residents of Snell and Sunshine Houses will soon be bussed everywhere on campus. There will also be a traffic guard at the intersection of the road and the house driveways.
The contractors will also be working on cutting the new road for the residential area into the existing hillside.
Upcoming Parking ChangesEffective immediately, all Springbrook staff and visitors are required to have a parking permit to park on Springbrook's Main Campus or Krol's lot. All Main Campus employees are issued one parking permit. If you have more than one vehicle, please provide Jennifer or Jessica with secondary/tertiary vehicle information. If you have any questions, please call Jennifer at Ext. 302 or Jessica at Ext. 316.
Contractor HQ
The site contractor will be working on Work Zone #1 (in the field across from the school) to prepare for job trailers and the building material staging areas. This area is now fenced off and is off limits to staff, residents and visitors.